Until then, the Baltic States’ power system was part of Russia’s interconnected power system, which posed a geopolitical and energy security risk. This is because Russia controlled one of the most important parameters of our power system – frequency – and thus the eastern neighbour had the ability to influence the operation of the power system in the Baltic States.

EU kaasrahastus

 

Synchronisation Information Day 28 November 2024 

Why synchronise?

First, the transition to synchronous operation with the Continental Europe Synchronous Area mitigates the risk that dependence on the Russian energy system and frequency area could be used against us. Secondly, the Baltic States are politically and socio-economically part of Western Europe, so it is entirely logical that the power system is also part of the Continental Europe Synchronous Area. This will reduce the risks associated with system management and improve the energy security of Estonian people and companies.

In addition to energy security, Estonia’s greater connectivity will also improve the international competitiveness of its economy. During synchronisation, new markets and products will emerge alongside existing electricity markets, increasing the opportunities for local electricity producers to sell electricity.

How does synchronisation take place?

To mitigate risks and expand the market, we have taken steps over the years to disconnect the power systems of Estonia, Latvia, and Lithuania from Russia’s and connect to the Continental European electricity network and the corresponding frequency area by the beginning of 2025 at the latest. Synchronisation is a joint and extremely high priority effort for the three Baltic States and Poland.

For synchronisation, the Baltic States reinforced their electricity networks and connections. Elering reconstructed the powerful 330-kilovolt power lines that start in the Narva region and head to Latvia near Valga. Similar reinforcements were also made in the power systems of Latvia and Lithuania.

To ensure frequency stability, synchronous compensators that add inertia to the system are being built in all Baltic States, and the power system, IT systems, and control systems for existing direct current connections are being upgraded.

In addition to new infrastructure and systems, the synchronisation will improve the interoperability of the control centres of the Baltic States and add additional know-how for independent management of the electricity network.

Project financing

Synchronisation will cost the Baltic States and Poland a total of approximately 1.6 billion euros, of which Estonia’s share is 298 million euros. Investments are divided into three rounds and, due to the high priority set by the European Commission, the projects will be financed to a maximum of 75% from the Connecting Europe Facility (CEF) funds. The remaining 25% of the required investments will be covered by congestion charges in Estonia.

The total investment volume of the first financing round in the Baltic States was approximately 430 million euros. In Estonia, as part of the first round, domestic electricity networks were reconstructed, and one synchronous compensator was built. Similar to Estonia, domestic network connections were improved, and synchronous compensators are also being built in Latvia and Lithuania.

The volume of the second round of investments in the Baltic States and Poland was approximately 700 million euros, which included the construction of two synchronous compensators in Estonia. The investments finance the construction of synchronous compensators in the other Baltic States and the construction of a direct current connection between Lithuania and Poland, along with the necessary network reinforcements.

The total investment volume of the third round in the Baltic States and Poland was 230 million euros. In Estonia, the investment objects of the third round include upgrades to the IT, control and monitoring systems of the control centre, upgrades to the management and control systems of EstLink 1 and 2 submarine cables, and improvement of the operational continuity of substations. In the other Baltic States and Poland, third-round investments include reconstruction of high-voltage lines, further development of substations, construction of battery-based energy storage systems in Latvia, and upgrades to IT systems.

In Estonia, a total of approximately 30 investment projects are being financed as part of synchronisation.

See how the project was implemented over the years:

 

 

Synchronisation in brief:

 

Baltic synchro

Projektide ajakava 2025. aastani

 

Benefits for market participants

For electricity producers and traders, synchronisation opens up a larger and more flexible market, allowing them to offer new types of energy market products and services and expanding export potential. New markets are emerging alongside existing ones, increasing the opportunities for electricity producers to sell electricity. Since electricity trade with Russia and Belarus came to an end in 2022, access to new markets is also of crucial importance for market participants.

System operators bring new products to the electricity market, which give market participants the opportunity to offer new services. Such services include, for example, the frequency maintenance reserve service and the automatic frequency restoration reserve. System operators involve market participants in the launch of new products to meet their capabilities and expectations.

Benefits for the consumer

Synchronisation primarily ensures better security of supply for consumers, but also a sense of security that Estonia itself, not Russia, has control over the energy system. Additionally, European Union investments make it possible to reconstruct depreciated high-voltage lines without the need for additional funds that would mean an increase in network fees. The transition from one frequency area to another occurs unnoticed by the end user, and the quality and continuity of network service improves.

Environmental impact

Estonia has joined the goal of carbon neutrality, which aims to slow down global climate change. It is therefore unthinkable to invest in renewable energy in our country and at the same time consume electricity from third countries with unknown environmental impacts. Carbon emissions cannot be reduced if they are released into the air across borders. Synchronisation eliminates the risk of potential carbon leakage and improves the ability to generate electricity from renewable sources.

Preparedness for emergency synchronisation

The Baltic States and Poland have prepared for a situation where desynchronisation from Russia may occur exceptionally. To this end, Elering has agreed on specific activities and protocols with the system operators of the Baltic States and Poland on how to connect to the Continental Europe Synchronous Area as safely and quickly as possible. This ensures security of supply for consumers and protects the security and economic interests of the States.  In this case, the emergency synchronisation would take place within hours, unnoticed by the end consumer.

In simplified terms, the desynchronisation/synchronisation process is as follows:

  • The Baltic States are desynchronised from the Russian and Belarussian frequency area (IPS/UPS), as a result of which the inertia and frequency of the Baltic States’ power system are no longer controlled from Russia.
  • The Baltic States operate as an island, during which the necessary inertia is ensured by local capacities and resources.
  • The Baltic States are synchronised with the Continental Europe Synchronous Area.

Elering is continuously working in cooperation with partners in Latvia, Lithuania and Poland to increase preparedness for emergency synchronisation. To this end, the following activities have been carried out:

  • 400/330kV AC transformers have been installed at the Alytus substation in Lithuania, ensuring technical preparedness for emergency synchronisation via the LitPol link within a few hours.
  • Agreements have been entered into with Nordic system operators to receive frequency support through direct current connections through the EstLink 1, EstLink 2 and NordBalt cables.
  • Regular training of system operator control centres is being carried out for a situation where emergency desynchronisation occurs by Russia and Belarus.
  • A legal and technical framework has been established for emergency synchronisation with Continental Europe.

Mitigation of risks

The probability and impact of possible risks materialising are continuously assessed at Elering in order to prevent and mitigate their negative impact on the activities necessary for synchronisation.

Hannes Kont

Director of the Synchronisation Programme /Head of Synchronisation Unit

+372 715 1248

Project overview

Synchronous compensators

Elering built synchronous compensators at the Püssi, Kiisa and Viru substations and they are used for frequency control.

According to studies and electricity market changes, the Baltic power system does not have the necessary inertia after disconnection from the Russian frequency area to ensure frequency stability and the required rate of change of frequency. Because of this, we built three synchronous compensators in Estonia, which help to control frequency.

In the Estonian context, the introduction of synchronous compensators means that the need to keep Narva power plant modules operating outside the market to ensure frequency is reduced, which entails significant costs.

Elering built synchronous compensators at the Püssi, Kiisa and Viru substations.  The function of synchronous compensators is to add inertia to the system to slow down the frequency change and enable the implementation of subsequent measures in the frequency control process, for example in the event of emergencies. The synchronous compensators to be built have high reliability and, in addition to inertia, support the network with short-circuit power and reactive energy compensation.

A total of nine synchronous compensators will be built in the Baltic States. In Estonia, synchronous compensators were built by the Estonian branch of Siemens Energy Oy and Siemens Energy Global GmbH & Co. KG. All synchronous compensators manufactured in Estonia are identical in design and operating principles, which simplifies maintenance and allows for the construction of equipment in the shortest possible time frame.

Püssi synchronous compensator station

The first synchronous compensator station was connected to the network in May 2023.  Of the nine synchronous compensators to be built in the Baltics, Püssi was the first to be completed, thereby helping to ensure frequency stability.

Kiisa synchronous compensator stationnkompensaatorjaam

The second synchronous compensator station in Kiisa was completed in January 2024.

Viru synchronous compensator station

The third and final synchronous compensator station in Estonia was completed at the Viru substation in June 2024.

 

TIMELINE:

Construction of synchronous compensators

Activity

Deadline

Start of the procurement process

18.05.2020

Entry into a contract

16.12.2020

Start of work at Püssi station

01.01.2021

Start of work at Kiisa station

01.05.2022

Start of work at Viru station

01.05.2022

Completion of work at Püssi station

01.05.2023

Completion of work at Kiisa station

01.01.2024

Completion of work at Viru station

01.06.2024

 

 

Transport and installation of the Viru synchronous compensator generator, September 2023:nkompensaatori generaatori transport ja paigaldus, september 2023:

 

Transport of the Viru synchronous compensator transformer, September 2023:

 

Preparing the Kiisa synchronous compensator generator for installation, May 2023:

 

Transport of the Kiisa synchronous compensator generator from the Port of Paldiski to Kiisa, May 2023:

 

Arrival of the basic equipment of the Kiisa synchronous compensator in April 2023:

 

Arrival of the equipment of the Püssi synchronous compensator in June 2022:

Read more:

4 June 2021 Article about synchronous compensators: How is frequency and short-circuit current generation ensured in the Estonian energy system? (in estonian)

16 December 2020 Elering establishes three synchronous compensator plants to connect to the Continental European power system

High-voltage lines

Elering reconstructed old overhead lines and line corridors to increase the capacity of power lines.

Separation from the Russian power system means that the option to direct some power flows through the Russian power system disappears, meaning that all the power transmitted between Estonia and Latvia will be transferred only to the lines between Estonia and Latvia. Reconstructing the lines will maintain capacity at the existing level and help to avoid restrictions in the north-south transit. In summary, after synchronisation, we will have a new network that is at least as strong as before and we will completely eliminate the influence of third countries on inter-market trading in the Baltic States.

Elering chose reconstruction instead of building new lines to ensure timely completion of projects, thereby reducing potential costs. When reconstructing lines, it is important to keep in mind that sufficient transmission capacity is guaranteed in all situations in the event that some lines fail (n-1 situation), which is why it is not possible to reconstruct all lines simultaneously.

Lines L300/L301 together with lines L353/L354 form a parallel line corridor between Estonia and Latvia. The reconstruction of the lines was necessary to strengthen the connections between the Estonian electricity system and the rest of the power system, to create the prerequisites for synchronous operation with the European power system. The lines play an important role in allowing manufacturers to enter the Estonian market at a lower price. Since the 330 kV lines in Estonia were built in the 1950s and 1960s, their lifespan was coming to an end and the need for renovation was great.

Reconstruction of the Baltic-Tartu (L300) 330 kV overhead line

The reconstruction of the Baltic-Tartu 330 kV overhead line began in 2020. The line was completed and energised in February 2023.

 

TIMELINE:

L300 Baltic-Tartu

Activity

Deadline

Start of the procurement process

02.01.2019

Entry into a contract

30.11.2020

Start of construction work

12.04.2021

Completion of construction work

01.03.2023

 

 

Dismantling work of the L300 Baltic-Tartu line:

Erection of a new tower in Iisaku, June 2022:

 

Reconstruction of the Tartu-Valmiera (L301) 330 kV overhead line

The reconstruction of the Tartu-Valmiera line began in autumn 2021. The line was energised together with Latvian partners in May 2023.

 

TIMELINE

L301 Tartu-Valmiera

Activity

Deadline

Start of the procurement process

02.01.2019

Entry into a contract

30.11.2020

Start of construction work

20.09.2021

Completion of construction work

01.06.2023

 

 

Reconstruction of the Baltic-Tartu and Tartu-Valmiera 330 kV overhead lines, 2021–2023:

 

Reconstruction of the Viru-Tsirguliina (L353) 330 kV overhead line

Similar to the Baltic-Tartu-Valmiera line, the Viru-Tsirguliina-Valmiera 330 kV overhead line was also reconstructed. Even before the start of synchronisation operations, the 11.48-kilometer section of the Tsirguliina-Valmiera (L354) line located on Estonian territory was reconstructed in 2015. During the reconstruction, the cable was replaced and the clearance was adjusted.

The reconstruction of Viru-Tsirguliina (L353) was completed in November 2024.

Elering energised the important Viru-Tsirguliina power connection for synchronisation | Elering

 

TIMELINE:

L353 Viru-Tsirguliina

Activity

Deadline

Start of the procurement process

01.08.2020

Entry into a contract

02.06.2021

Start of construction work

01.06.2023

Completion of construction work

31.12.2024

 

Upgrades to the control systems of EstLink 1 and EstLink 2

The EstLink 1 and EstLink 2 submarine cables are some of the most important connections between the Baltic States and the Nordic countries, which provide support for frequency regulation for our power system where necessary.

Due to the requirements and functionalities associated with synchronisation, it is necessary to upgrade the command and control systems of the converter stations of both submarine cables located on the mainland.

The depreciated hardware of the EstLink1 control systems will be replaced, and the control and protection system of the entire converter will be updated and brought in line with modern requirements and needs.

 

TIMELINE OF ESTLINK 1:

Upgrades to the control systems of EstLink 1

Activity

Deadline

Start of the procurement process

30.07.2022

Entry into a contract

21.11.2023

Completion of work

30.09.2027

 

 

TIMELINE OF ESTLINK 2:

Upgrades to the control systems of EstLink 2

Activity

Deadline

Start of the procurement process

01.03.2023

Expected completion of work

31.12.2025
Upgrades to IT, data communications and control systems

The projects and investments necessary for synchronisation include not only infrastructure projects, but also require the development of the IT and communication capabilities of the electricity control system.

As part of this, the power system planning and control systems (SCADA/EMS) will be updated, which will make it possible to plan, monitor and control changes in the power system remotely. As a result of the update, the control centre’s ability to assess and control the power system in real time will be improved.

It is also important that real-time metering data and data exchange for monitoring the stability of the power system and frequency control are of high quality, reliable and guaranteed consistently. To this end, data communication and monitoring systems at critical substations will be replaced with newer and more reliable equipment that ensures continuous transmission of data related to voltage, current, and frequency.

Furthermore, various generation and consumption forecasting systems will be updated, and new balance administration software and outage planning software will be procured and implemented.

 

TIMELINE:

Upgrades to IT, data communications and control systems

Activity

Deadline

Start of the procurement process

01.12.2021

Entry into a contract

01.02.2022

Start of development work

01.02.2022

Completion of development work

01.12.2025