The following appendices must be submitted together with the connection application:

  • a location plan indicating the location of the production device and the requested connection point with the coordinates;
  • schedule of the client's activities until gas injection; 
  • parameters for connecting a consumer and/or producer;
  • daily profile of consumption and/or generation during peak load;
  • daily profile of consumption and/or generation in the summer and winter periods;
  • technological diagram and description of the power-generating facility;
  • details and specification of the production device.

Elering sends an invoice for the processing fee for connection to the client within three working days from the submission of the application. Elering will inform the applicant of deficiencies in the connection application within ten working days from the payment of the processing fee. The client has 20 working days from the submission of Elering’s notice to remedy the deficiencies in the connection application. If there are no more deficiencies in the connection application or its correction, Elering will notify the client of the absence of deficiencies or of the acceptance of the connection application upon their elimination within ten working days.

The connection offer is made to the client within 90 days from the acceptance of the connection application.

The connection contract shall specify:

  • locations of the connection and metering point(s);
  • work in the transmission system necessary for establishing the grid connection;
  • consumption or generation conditions of the grid connection to be established;
  • deadline for completion of the connection;
  • the amount of the connection fee and terms of payment;
  • conditions for ensuring grid connection;
  • terms and conditions of amendment and termination of the connection contract;
  • other terms and conditions.


The connection offer is valid for 180 days, during which the client must sign the connection contract.