The consumption of natural gas dropped in October by 13 per cent to 390 gigawatt-hours as a result of the warmer than usual weather. Natural gas imports to Estonia were 13 per cent less than last...
Elering has signed the companies chosen in two public procurements, Merko Infra and Connect, to contracts for the construction of new electrical submarine cables in the Suur and Väike Vain straits...
In October, electricity exchange prices fell in all bidding areas of the Nordic countries’ Nord Pool exchange. Prices had entered a downward trend already in the previous month. The price was highest...
Elering’s income for the first nine months of this year was 100.4 million euros, operating profit was 18.2 million euros and net profit was 6.5 million euros. Net profit grew by 16 per cent year-over...
Consumption of natural gas was reduced by 9% to 589 gigawatt-hours in the last quarter. According to the Estonian Weather service, the air temperature of the past three months was 2-2.7 degrees above...
In Q3, power generation grew by five per cent compared to the same period last year; quarterly output was 2,573 gigawatt-hours. Consumption increased by 1 per cent to 1865 gigawatt-hours. In the month...
In Q3, Estonian power plants generated 402 gigawatt-hours of renewable energy, which was more than one-firth more than in the same period last year. Renewable energy made up 19 per cent of the total...
The transmission system operators (TSOs) in Estonia, Latvia and Finland - Elering, Conexus Baltic Grid, Gasum and Baltic Connector – have signed a Memorandum of Understanding on the matters to be...
On Wednesday, Elering and the Latvian and Lithuanian TSOs filed a financing application with the European Commission for funding the first stage of investments for synchronizing the Baltic electricity...
Last week, construction activity on the third Estonia-Latvia power connection being established by Elering kicked off near Pärnu. In the course of the works, Empower AS and Leonhard Weiss Energy AS...