The connection conditions set out procedural and technical rules, principles and conditions for the following persons, proceeding from the Electricity Market Act, Network Code on the Functioning of the Power System, the Grid Code, the RfG, and the DCC.

  • customers connecting to the national transmission system;
  • consumers and producers connected to the national transmission system and to whose power grid, type A, B, C or D generating modules will be connected;
  • consumers connected to the national transmission system and to whose power grid a electricity consumer that is not self-supply of generating module will be connected,and which requires a modification and/or configuration necessary for fulfilling the conditions described in clause 5.6;
  • to distribution grid companies to whose power grid type A, B, C, D generating modules will be connected;
  • producers whose type B, C or D generating modules will be connected to the distribution grid company’s power grid.

Connection processes launched starting 1 July 2019 are governed by the standardized terms and conditions for connecting to Elering’s electricity transmission system (hereinafter connection conditions) approved by the Competition Authority’s decision no. 7-10/2019-003 of 30 May 2019.

Elering amended point 1.1.2 (table „List of Annexes to be submitted together with the connection application“) of appendix 1 of the standard terms and conditions of connection to the electricity transmission system of Elering AS (hereinafter the connection conditions) on 1 July 2019.

The amendments provide for specifications to the applicable wording of the connection conditions with the purpose of which is to ensure legal clarity after the entry into force of the new revision of the Network Code on the Functioning of the Power System on 22.06.2024 which amended §19 „Connection application and amendment of the production and consumption conditions“.

The aforesaid amendment entered into force on 10 August 2024.

Categorization of generating modules:

  • type A generating modules – voltage at the connection point is under 110 kV and the electrical maximum capacity is less than 0.5 MW;
  • type B generating modules - voltage at the connection point is under 110 kV and the electrical maximum capacity is at least 0.5 MW but under 5 MW;
  • type C generating modules - voltage at the connection point is under 110 kV and the electrical maximum capacity is at least 5 MW but under 15 MW;
  • type D generating modules - voltage at the connection point at least 110 kV and the electrical maximum capacity is at least 15 MW.

Amendments to the connection conditions on 01.07.2019.

Standardized forms used during the connection process
Data submitted in the connection application
Energisation application
Energisation plan
Application of the connection of a prototype device

General data of power generating module

 

Energisation and synchronisation applications

Energisation application

Synchronisation application

 

 

Varasemad liitumislepingu tüüpvormid
Dokumendi nimi Kehtivus
Põhivorguga liitumise tingimuste lisa 2 - liitumislepingu tüüpvorm 01.06.2017
Põhivõrguga liitumise tingimuste lisa 2 - liitumislepingu tüüpvorm 01.01.2013 - 31.05.2016

 

 

 

 

Varasemad liitumislepingu tüüpvormid
Dokumendi nimi Kehtivus
Põhivorguga liitumise tingimuste lisa 2 - liitumislepingu tüüpvorm 01.06.2017
Põhivõrguga liitumise tingimuste lisa 2 - liitumislepingu tüüpvorm 01.01.2013 - 31.05.2016