The Estonian, Latvian, and Lithuanian prime ministers signed a joint declaration agreeing on the actions and the deadline for accelerating the connection to the continental European electricity grid...
This week, Elering energised the fully redeveloped Tartu-Valmiera high-voltage power line. It comprises one of the Estonian-Latvian electricity interconnections along with the Balti-Tartu high-voltage...
The fully upgraded Balti-Tartu high-voltage line was energised on Tuesday, which makes it the first of the investments completed within the scope of the major synchronisation project. The price of the...
Last week saw the arrival in Estonia and initial installation of key equipment required for the Püssi synchronous compensator, providing additional assurance that the first of the three such...
AST, Elering, Litgrid and PSE, the electricity transmission system operators (TSOs) of the Baltic countries and Poland, signed the grant agreement with the European Climate, Infrastructure and...
Elering will erect the second Estonian designer pylon named Sookurg for the high-voltage power line near Tartu within the framework of the major project of connecting Estonia to the European...