Production of electricity in Estonia grew in July by 7 per cent from the same period a year ago, reaching 822 gigawatt-hours for the month. Consumption also grew year-over-year by six percent...
Power flows of electricity from Estonia to Finland grew in July compared to previous months. In July, 50 per cent of the electricity power flows between Estonia and Finland were in the direction of...
In Q2, Estonia’s power plants generated 376 gigawatt-hours of renewable energy and renewable energy made up 17.2 per cent of total power consumption in Estonia. Estonia has set a renewable energy...
Elering and Elektrilevi, having held joint procurements, entered into contracts with Merko Infra AS for building the Kiini 110 kilovolt substation and expanding the Paldiski 110 kilovolt substation...
In the next four years, Elering and its project partners will develop a flexibility services platform that connects Estonian, Finnish and Latvian electricity markets and that in future can be used...
Elering concluded an agreement with Merko Infra AS for expanding the switchgear of the 330 kV Harku substation, which as part of the third power connection between Estonia and Latvia has key...