Elering has taken control of renovation work performed by Merko Infra AS on Sindi and Vändra substations, which cost 3.17 million euros. At the Sindi 330/110-kilovolt substation, Elering had the...
Last week, construction activity on the third Estonia-Latvia power connection being established by Elering kicked off near Pärnu. In the course of the works, Empower AS and Leonhard Weiss Energy AS...
Elering has launched a public procurement to find a constructor for the third Estonia-Latvia electricity interconnection. “It is truly remarkable that the Estonia-Latvia electricity interconnection –...
Elering has signed a financing agreement worth 112 million euros with the European Commission to finance the construction of the third Estonian-Latvian electricity connection. Elering will cover its...
Estonian transmission system operator Elering, Latvian independent system operator AST and Latvian transmission system owner LET signed on 21st of February a memorandum of understanding in order to...