Estonian electricity system operator Elering and the Latvian system operator AST formally launched the third Estonian-Latvian electricity connection on Wednesday, which inter alia creates the...
Elering has energised and commissioned the power lines comprising the third Estonian-Latvian electricity connection and the new connection will be usable by the market as of the first day of the next...
Elering has entered into a contract with Empower AS for the construction of the power line section from Kilingi-Nõmme substation to the Estonian-Latvian border within the framework of the project for...
On Tuesday, Elering is to enter into an agreement with the European Commission for channelling more than 140 million euros from the Connecting Europe Facility (CEF) into the first phase of the...
On Tuesday, Elering entered into construction contract with Merko Infra for the expansion of the Sindi 330-kilvolt substation. The work is a part of the project to establish the third Estonia-Latvia...
Elering has signed a contract with AS Connecto, the winner of a public procurement for the renovation of the 110-kilovolt Risti substation on the Harku-Lihula-Sindi line, for approximately 1.5 million...