Electricity transmission service prices from 01.01.2025
Tariff category |
Voltage of 330 kV |
Unit |
Network fee |
---|---|---|---|
|
Price package I |
|
|
A1 |
Transmission fee |
EUR/MWh |
6,62 |
T1 |
Consumption point fee |
EUR/point of consumption/year |
84 888,57 |
V1 |
Capacity fee |
EUR/MVA/year |
3 382,04 |
|
Price package II |
|
|
T4 |
Consumption point fee |
EUR/point of consumption/year |
84 888,57 |
V4 |
Capacity fee |
EUR/MVA/year |
10 495,39 |
Tariff category |
Voltage of 110 kV |
Unit |
Network fee |
---|---|---|---|
|
Price package I |
|
|
A2 |
Transmission fee |
EUR/MWh |
11,57 |
T2 |
Consumption point fee |
EUR/point of consumption/year |
10 742,41 |
V2 |
Capacity fee |
EUR/MVA/year |
5 902,32 |
|
Price package II |
|
|
T5 |
Consumption point fee |
EUR/point of consumption/year |
10 742,41 |
V5 |
Capacity fee |
EUR/MVA/year |
18 348,36 |
Tariff category |
<Voltage of 110 kV |
Unit |
Network fee |
---|---|---|---|
|
Price package I |
|
|
A3 |
Transmission fee |
EUR/MWh |
12,57 |
T3 |
Consumption point fee |
EUR/point of consumption/year |
25 883,30 |
V3 |
Capacity fee |
EUR/MVA/year |
6 695,67 |
|
Price package II |
|
|
T6 |
Consumption point fee |
EUR/point of consumption/year |
25 883,30 |
V6 |
Capacity fee |
EUR/MVA/year |
19 622,77 |
Tariff category |
Reactive energy fee |
Unit |
Network fee |
---|---|---|---|
R |
Reactive energy fee |
EUR/Mvarh |
1,76 |