At a meeting of Estonian, Latvian and Lithuanian TSOs held yesterday, on 4th of February in Riga, it was decided to postpone the Baltics' power system isolated operation test. The decision came after...
By agreement between the transmission system operators of the Baltic states – Elering, AST and Litgrid – a test of the isolation of the countries’ electricity system from the Russian power system and...
One of the most important preparation steps towards synchronisation – the Baltic power system isolated operation test will take place in 2019. The isolated test is the one of the main action...