Generating unit tests
Upon completion of the generating unit, the client must synchronise it with the electricity network.
Prerequisites for synchronisation
The following conditions must be met before synchronisation:
- Elering has issued an energisation operational notification, and the client has obtained an approval for and verified the functioning of signals and controls in Elering’s direction at least seven days before the requested date of synchronisation of the generating unit.
- The grid connection to be ensured by Elering and the consumption point are ready to be taken into generation-oriented use.
- The client’s electrical installation is ready to be taken into generation-oriented use and the client’s generating unit is ready to be synchronised.
- The client submits a synchronisation application to Elering at least seven days before the requested date of synchronisation of the generating unit.
- Elering has approved the comprehensive electrical design documentation for an electrical installation drawn up by the client, which has been approved by Elering seven days before the requested date of synchronisation. The electrical design documentation includes, among other things:
- type test reports for every type of power-generating facility;
- report on the simulation of cooperation between the generating unit and the electricity network;
- PSS/E and PSCAD models.
- Elering has approved the acceptance test plan for the generating unit drawn up by the client, which must be approved by Elering seven days before synchronisation.
- In the case of synchronous generators, Elering has approved the results of no-load tests of the generating unit, which must be submitted at least fourteen days before the requested date of synchronisation of the generating unit.
- The client has made all the payments required by the date of energisation to Elering and properly performed all other obligations provided for in legislation and the contract entered into between the client and the transmission system operator.
- The client has obtained an approval for and verified the functioning of signals and controls in Elering’s direction and the form for information volume table provided in section 5 of this guideline at least seven days before the requested date of synchronisation of the generating unit.
- A temporary network contract has been entered into, permitting the generation-oriented capacity of the grid connection.
Following synchronisation, the client verifies the correct functioning of all the signals, including measurements and controls, set out in the technical design documentation with the energy system control centre and submits the signal test report to Elering following the synchronisation.
The verification and certification of the conformity of a generating unit shall take place in accordance with the provisions of the connection contract, the Connection Conditions, the RfG, the Grid Code, and the Electricity Market Act. The conformity of a generating unit with the established requirements is assessed at the connection point between Elering and the client.
Carrying out tests
Tests are generally carried out in three stages:
- quality measurements;
- functional tests of the generating unit, after which the client submits a report on the test results to the network operator and the network operator gives its assessment on the report. Elering has drawn up a sample test report for power park modules and a sample test report for synchronous power-generating modules, which can be used as a basis for drawing up the test report;
- FRT test.
Certification of conformity
Once all the agreed tests have been successfully carried out, Elering shall provide an assessment of the conformity of the client’s generating unit with the requirements set out in the Grid Code, the RfG, and the connection contract. The final operational notification is issued by Elering once the requirements specified in the connection conditions have been met.