Skip to main content

Elering has amended its connection conditions, which will come into force on 1 July in connection with the entry into force of European Commission regulation no. 2016/631 (hereinafter RfG) and the network code on functioning of the electrical system (EsT VE) on 27 April 2019, in order to set forth more precisely the activities of and requirements for Elering and new customers during connection proceedings in accordance with RfG and EsT VE.

In addition, Elering’s aim was to make it easier and faster for customer to connect to the network, articulate more clearly the requirements for connection conditions and change the document structure so that it is more comprehensive and comprehensible. 

 

Forms of data transmitted during the connection process
Data submitted by the application for connection  
Annex 3- Testing.docx  
Annex 5-Guide for writing electrical and modelling requirements for electrical installations.docx  

 

 

Earlier technical requirements and rules for connecting to the grid
Document Valid
Annex 1 - technical requirements and rules (Est) 24.02.2014 - 31.05.2016
Annex 1 - technical requirements and rules (Est) until 24.02.2012
Technical requirements and rules (Est)  
Technical requirements - tables (Est) 01.01.2013 - 31.05.2016
Technical requirements - tables (Est)  

 

Earlier standard contracts
Document Valid
Annex 2 - standard contract (Est) 01.01.2013 - 31.05.2016

 

Earlier methodologies for calculating the connection fees and the fee for changing production or consumption conditions 

Document Valid
Calculating the connection fees and the fee for changing production or consumption conditions (Est) until 31.05.2016
Methodology for calculating the connection fees and the fee for changing production or consumption conditions (Est) 2015

 

 

Earlier technical requirements and rules for connecting to the grid
Document Valid
Annex 1 - technical requirements and rules (Est) 24.02.2014 - 31.05.2016
Annex 1 - technical requirements and rules (Est) until 24.02.2012
Technical requirements and rules (Est)  
Technical requirements - tables (Est) 01.01.2013 - 31.05.2016
Technical requirements - tables (Est)  

 

Earlier standard contracts
Document Valid
Annex 2 - standard contract (Est) 01.01.2013 - 31.05.2016

 

Earlier methodologies for calculating the connection fees and the fee for changing production or consumption conditions 

Document Valid
Calculating the connection fees and the fee for changing production or consumption conditions (Est) until 31.05.2016
Methodology for calculating the connection fees and the fee for changing production or consumption conditions (Est) 2015

What are you looking for?